Tuesday, September 16, 2014
The turbidity barrier arrived this morning and was temporarily stored in the driveway of the project's field office at the end of West 12th Road. Work has started on the removal of some decking on the north side of the bay outfall to allow for the tie-in of a cofferdam.
Remember, effective tomorrow morning, Wednesday, September 17th, parking and driveway access will be restricted on the south side of West 12th Road (the side with the even # addresses), between the hours of 6:00 a.m. and 7:00 p.m.
By the way, the ponded water in the street is from this morning's rain and not the tide.
By the way, the ponded water in the street is from this morning's rain and not the tide.