Staff from several of the agencies/firms/utilities involved in the pending Broad Channel Flood Mitigation Project (HWQ 1182A) regarding new bulkhead and street raising on West 11th, 12th and 13th Roads were present on West 12th Road earlier today acquainting themselves with the street in preparation the pending Broad Channel Flood Mitigation Project (HWQ 1182A) regarding new bulkhead and street raising on West 11th, 12th and 13th Roads.
Present for the street inspection were representatives from:
N.Y.C. DOT
N.Y.C. DDC
The RBA Group [design firm]
E.I.C. Associates [general contractor]
Verizon
Con Edison