(Photo by Peter J. Mahon - Mon. 11/8/2010) |
As we reported last week, things are moving along at at quick pace regarding the flood mitigation project for West 12th Road.
Delayed by tidal street flooding last week, workcrews set up at the end of the block earlier today to conduct test borings of the street to obtain data regarding the composition of the sub-strata in order to provide the RBA Group information to determine how best to proceed with raising our street, installation of sub-street storm water chambers, etc.
Test borings are scheduled to be conducted on W11th, W12th and W13th Roads.
YAY!
ReplyDelete